Oakfield solar farm

In the beginning of 2016 we started two projects for one of our clients with conditions to finish mechanical installation and mounting of just a bit over 60 000 solar modules in 30 days. The job was made even more complicated because of the floods in the area, damaged roads and bridges, knee deep mud on the sites, a lot of complicated under and overground infrastructure…all that complications and restrictions were adding to the pressure, but in the end we did it, we met our deadlines with a couple of days to spare, and two more projects are up and running in the North West

Address:
Newton-with-Clifton Lancashire, UK
Capacity:
4.77 MW